A large electrically heated house, two EVs, a workshop, a heated pool: the cases that really justify going past 200 amps, and the ones where a load controller is enough.

Published October 11, 2026Sources checked September 11, 2026By STM-Électrique’s master electriciansRBQ licence 5815-0137-018 min read

In short

  • Past 200 amps, you’re no longer talking about a panel: you’re talking about redoing the whole service.
  • Past 200, the next step is usually 320 amps, the largest service metered directly at the meter base.
  • The load calculation isn’t optional: it’s what justifies the capacity you ask for.
  • Past 200 amps, the electrician can no longer disconnect the service on their own: Hydro-Québec becomes part of the schedule.
  • A bigger service doesn’t raise your electricity bill. Capacity uses nothing.

Most houses that feel cramped on 200 amps aren’t. They’re short on breaker spaces, or their load is poorly distributed. Both problems can be fixed without redoing the service.

But real cases do exist. This guide helps you tell them apart, because the price gap between “fixing it another way” and “going to 320 amps” runs into the thousands of dollars.

When 200 amps really isn’t enough

In our experience on the North Shore and in Laval, a 200 amp service is truly outgrown when several of these add up:

  • A large electrically heated house, over 3,000 square feet, with several zones
  • Two electric vehicles charging in the evening, with no load sharing
  • A detached garage or workshop with heavy tools, a compressor or a welder
  • An electrically heated pool, often with a spa
  • An accessory dwelling unit or an addition with its own heating load
  • A central heat pump with electric backup heat that piles on top of everything else in January

One of these on its own almost never justifies going past 200 amps. Three or four together, yes.

Before going bigger, we always look at a load controller first. It keeps two large loads from running at the same time (the EV charger and the range, for example), and it lets many houses stay at 200 amps. It costs a fraction of the price of a new service, and it’s often the right answer.

320 or 400: the difference

These two numbers actually describe the same equipment from two angles.

In a house, the standard setup past 200 amps is a meter base rated 400 amps, with a continuous capacity of 320 amps. That’s the usual safety margin: you don’t run a service at its full rating continuously. That’s why people commonly say “320 amps” for a home, and “400 amps” when they mean the equipment rating.

A true 400 amp continuous service does exist, but you’ll mostly see it in commercial, institutional and multi-unit buildings. On a house, it’s rare, and it needs an even stronger load calculation to back it up.

Need200 A320 A400 A
Electrically heated house, normal useEnoughNot neededNot needed
One EV chargerAlmost always enoughNot neededNot needed
Two chargers with load sharingOften enoughSometimesNot needed
Two chargers at full power, large houseNot enoughThe usual solutionRarely required
Heavy detached workshop + the whole houseNot enoughThe usual solutionDepends on the calculation
Heated pool + spa + heating + chargersNot enoughOften enoughDepends on the calculation
Apartment building, commercial shop, several unitsNot enoughDepends on the calculationWhere 400 A usually belongs

The possible setups

Going past 200 amps doesn’t mean installing a panel twice as big. In practice, three setups keep coming up.

Two 200 amp panels fed by a 400 amp meter base. It’s the most common setup in homes. Power arrives at a single meter base, then splits toward two service boxes, often one for the house and one for the garage, the workshop or the accessory unit.

A main panel and a remote subpanel. When the extra load is concentrated in one place (a detached garage, for example), we run a dedicated feeder to a subpanel instead of stretching many circuits over a long distance.

Keeping the 200 amps with load management. It’s the third option, and it’s the one we choose most often when the calculation allows it. It touches neither the service entrance nor the meter.

What the load calculation has to show

A load calculation isn’t an estimate or an electrician’s opinion. It’s a standard method, set out in the Code, that adds up the living area, the heating, the fixed appliances and the special loads.

Past 200 amps, it matters even more: it’s what justifies the capacity you ask for, to the inspector and to Hydro-Québec alike. Since 2026, it must also include the load of EV chargers.

It has to show three things:

  • That the calculated load really exceeds what a 200 amp service can handle
  • That this load can’t be brought back under the limit with load management
  • That the capacity requested matches the need, with no needless oversizing

You should also know that Hydro-Québec has to confirm the capacity available on the grid at your address. In an older or already busy area, that isn’t automatic, and this check is part of the schedule.

Run the numbers: does your house go past 200 A?

Our calculator estimates your home’s load using the Code method, in two minutes. Past 200 A, it shows the estimated minimum service: 320 or 400 A.

Run the load calculation

Not sure about your service entrance?

We take a look, we price it, and the price is in writing before anything starts.

Send my quote request

What drives the cost up

The cost doesn’t follow the amperage in a straight line. It climbs in steps, because each threshold changes the nature of the job.

The whole service entrance. Mast, hardware, meter base, conductors: everything is larger and rated higher, so it costs more and is heavier to handle.

Two service boxes instead of one. Twice the equipment, plus the work of splitting the circuits between them.

Hydro-Québec’s schedule. This is the part few people see coming. The standard allows a master electrician to disconnect and reconnect the service themselves only up to 200 amps, at 120/240 V. Above that, Hydro-Québec has to step in, and the timeline is no longer in the contractor’s hands.

Distance and routing. A feeder to a detached garage crosses the yard: trenching, conduit, and putting the yard back in shape.

Grid capacity. If the area can’t supply it, there may be work on Hydro-Québec’s side, with delays and sometimes fees.

For reference: at STM-Électrique, a 200 amp service entrance and panel redone together on a single-family house come to around $2,900. A 320 amp service is well above that, because it’s a different job, and it’s priced after the visit and the load calculation, never over the phone.

Frequently asked questions

What’s the difference between 320 and 400 amps?

In a house, the two numbers often describe the same equipment: a meter base rated 400 amps with a continuous capacity of 320 amps. People say “320 A” for the capacity you can use and “400 A” for the equipment rating. A true 400 amp continuous service is found mostly in commercial and multi-unit buildings.

Do I need two panels?

It’s the most common setup: a single meter base feeding two 200 amp service boxes, often one for the house and one for the garage or workshop. It isn’t mandatory, but it’s the simplest and most widespread solution.

Can Hydro-Québec say no?

The capacity available on the grid at your address has to be confirmed. In an older or already busy area, the request may require work on Hydro-Québec’s side, with delays. So it isn’t a refusal in the strict sense, but it isn’t automatic either: it’s one of the first things we check.

Can a load controller make the upgrade unnecessary?

Often, yes, and it’s always the first thing we look at. A controller keeps two large loads from running at the same time, which brings the peak back under the limit of your existing service. It costs a fraction of the price of a 320 amp service. The load calculation tells you whether it’s enough.

How long does the installation take?

Longer than a 200 amp job, mainly because of the coordination with Hydro-Québec: above 200 amps, the electrician can no longer disconnect and reconnect the service themselves. The work on site is still in the range of one to two days; it’s the overall schedule that gets longer.

Will it raise my electricity bill?

No. It’s the most common mix-up. Your bill depends on the energy you use, not on the capacity available. A 320 amp service that powers exactly the same appliances as a 200 amp service costs exactly the same to run. Capacity is the width of the pipe, not the amount of water flowing through it.

Should I go bigger “just in case” while I’m at it?

Rarely. The price gap between 200 and 320 amps is significant, and the load calculation has to justify the capacity you ask for. If your actual project fits on 200 amps, with or without load management, going bigger is an expense, not a precaution.

Outgrowing 200 amps?

We do the load calculation, check the capacity available and tell you honestly whether a load controller solves your problem for a lot less.

4.9 from 535 Google reviews · RBQ licence 5815-0137-01 · Members of the Corporation des maîtres électriciens du Québec (CMEQ) · Free detailed quote

Sources

The figures and requirements cited in this guide come from the official pages below, consulted on September 11, 2026. Programs change: check the page’s last update date before you commit to any expense.