Meter stack in a commercial or mixed-use building

Shops on the ground floor, apartments above: why each unit has its own meter, when metering moves to transformers, and who deals with Hydro-Québec.

Get a quote

By the master electricians of STM-ÉlectriqueRBQ licence 5815-0137-01Sources checked on October 29, 2026

In short

In a building where shops and apartments share the space, the meter stack brings the meter bases of every account together on common busbars.

  • With separate metering, each residential or commercial unit has its own meter.
  • At 347/600 V, above 200 A, the meter is connected to voltage and current transformers.
  • The master electrician files the service request at the planning stage, then the declaration of work once everything is ready.
  • For a business or a plant, the shutdown usually lasts about 24 hours with us; for an apartment building, about 6 hours.
Jump to a section6
  1. One meter per unit
  2. Where the meters go
  3. Transformers
  4. Expanding or replacing
  5. The shutdown
  6. Frequently asked questions

One meter per unit

Separate metering means one meter for each residential or commercial unit in a building: the ground-floor shop and the apartments can each have their own.

For a given location and voltage, Hydro-Québec in principle accepts only one metering point per customer; the same customer can have more than one when its uses and rates differ.

A unit separated from its neighbours by fire walls counts as a separate building; it can therefore get its own service.

An industrial establishment, a complex structure or a self-contained unit can also get an additional service with a separate metering point; Hydro-Québec may then ask for a written attestation.

On the bill side, Hydro-Québec’s Rate G applies to contracts whose minimum billing demand stays below 65 kW; at 65 kW or more, the contract is no longer eligible.

Where the meters go

SituationWhat the Blue Book provides
Multiple-meter deviceOn the outside wall of the building it serves
Seven delivery points or moreA metering centre, if outdoor devices are not used
Building open only at certain hoursMetering installed outside the closed perimeter
In front of the service equipmentAt least 1 m of clear space

Every service box, panel and meter base carries the address or the unit number: that is what links each meter to the right business.

Metering transformers

Metering is chosen according to the voltage, the rating of the service box and the installed load.

VoltageMeter on a meter baseMeter on transformers
120/240 V320 A or lessMore than 320 A
120/208 V200 A or lessMore than 200 A
347/600 V200 A or lessMore than 200 A

These thresholds have exceptions, including dual-energy installations.

The split of tasks is set: the cabinet, the conduits and the meter support are installed by the master electrician, at the customer’s expense; the meters and transformers come from Hydro-Québec, which connects them.

The cabinet is for Hydro-Québec’s use only, with its own disconnect just upstream, and only those on its list of accepted products can be used.

Expanding or replacing

To add a single delivery point to an existing installation, one more individual meter base is allowed.

Beyond that, meter bases are best grouped on one or more multiple-meter devices, preferably with combination breakers.

Extra loads mean redoing the calculation for the feeders and the service upstream.

Meter stacks and switchgear are the commercial work we especially do.

A commercial meter stack to replace?

We examine the meter bases and the capacity; the price is written in the quote, at no charge.

Send my quote request

The shutdown

During the replacement, the building has no power: in an apartment building, usually about 6 hours with us. For a business or a plant, the shutdown usually lasts about 24 hours.

Hydro-Québec, not the master electrician, reconnects a transformer-rated meter: the date therefore depends on Hydro-Québec too.

In a shop, the timing of the shutdown is decided with the manager, and the job is divided so customers are disturbed as little as possible.

Frequently asked questions

Can the ground-floor shop have its own meter?

Yes. With separate metering, each residential or commercial unit has its own meter.

At what rating are transformers needed?

Above 200 A at 347/600 V or 120/208 V, and above 320 A at 120/240 V.

Who pays for the transformer cabinet?

The customer: the master electrician installs it at the customer’s expense, along with the conduits and the meter support. The meters and transformers are supplied by Hydro-Québec.

How long is the building without power?

For a business, usually about 24 hours with us; in an apartment building, about 6 hours. With a transformer-rated meter, Hydro-Québec does the reconnection: the date is set with Hydro-Québec.

Does the load calculation need to be redone?

Yes, if loads are added: the calculation for the feeders and the service upstream has to be redone.

A commercial meter stack to replace?

Meter bases, cabinet and Hydro-Québec requests: we take care of them, with the price written in the quote.

4.9 from 469 Google reviews · RBQ licence 5815-0137-01 · CMEQ members · Free detailed quote

Get a quote: commercial building

EN - Service request (English service pages)