The transformer set on the ground in front of a store or a building: when Hydro-Québec requires a substation on the property, who owns it, and what falls to the building owner.

Get a quote

By the master electricians of STM-ÉlectriqueRBQ licence 5815-0137-01Sources checked on November 13, 2026

In short

A pad-mounted transformer is a Hydro-Québec transformer substation set on the ground, on the property of the building it supplies.

  • A distribution substation (on a pad, on a pole, on a platform or in an adjoining vault) is needed when the service exceeds what the line supplies directly: service boxes totalling 600 A or more and a maximum current demand above 500 A, under the 2026 Electricity Conditions of Service.
  • The transformer belongs to Hydro-Québec; the pad and ducts that the owner builds belong to the owner; these works and the grounding are at the owner’s expense (Green Book, 5th edition, 2009).
  • Only Hydro-Québec connects the installation to its line (Green Book, 5th edition, 2009).
  • According to Hydro-Québec’s Green Book (5th edition, 2009), lead times can reach nine months after the required information is received.
Jump to a section10
  1. The terms
  2. When one is needed
  3. Who owns it
  4. Who pays what
  5. The pad and its surroundings
  6. The steps
  7. Who does what
  8. Dry-type transformer
  9. Our role
  10. Frequently asked questions

The terms

Around a building, the word “transformer” refers to three different devices.

  • Hydro-Québec’s distribution transformer supplies the building at low voltage from the line. Hydro-Québec calls it a distribution substation, whether it sits on a pad, on a pole, on a platform or in an adjoining vault. That is the subject of this guide.
  • Instrument transformers connect the meter of a large service: at 347/600 V, above 200 A, the meter is connected to voltage and current transformers. They are explained in our guide to the commercial meter stack.
  • The dry-type transformer, indoors, steps the building’s voltage down, for example from 600 V to 120/208 V.

The pad itself is the structure that holds the equipment above ground; it can belong to the customer or to Hydro-Québec.

A customer substation is a different case: a transformer substation that does not belong to Hydro-Québec, located downstream of the connection point, for medium-voltage service (Red Book standard).

When one is needed

Hydro-Québec’s Electricity Conditions of Service in force on October 1, 2026 set the threshold from the building’s service boxes:

  • Under 600 A in total: direct supply from the line.
  • 600 A or more: direct supply as long as the maximum current demand does not exceed 500 A, or 600 A for a dual-energy system in winter.
  • Beyond that: a distribution substation on the property, on a pole, on a pad, on a platform or in an adjoining vault.

The type of substation is chosen with Hydro-Québec (Green Book, 5th edition, 2009). Under the same standard, a pole-mounted substation is offered only if the line is overhead, and no longer at all once enrolment in an undergrounding program is confirmed.

For a school subsidized by the Ministère de l’Éducation, only pad-mounted and adjoining-vault substations are allowed (Green Book, 5th edition, 2009).

The same Green Book provides for the pad-mounted substation at 347/600 V up to 6,000 A from a 25 kV line, or up to 2,000 A from a 12.5 kV line.

When the current demand grows

A 347/600 V building whose service boxes exceed 600 A, supplied directly by the line or by a pole-mounted substation, can exceed its demand limit. Hydro-Québec notifies the owner, who then has 6 months to act.

The owner must put in place, at the owner’s expense, the civil works and equipment of a distribution substation other than pole-mounted.

If the limit is exceeded within 5 years of energization, the owner also reimburses Hydro-Québec for installing and removing its equipment, transformers included.

An overhead-underground service does not solve this case: the private pole never carries a transformer. See our page on underground electrical service.

Who owns it

The connection point marks the boundary between what belongs to Hydro-Québec and what belongs to the owner.

  • The distribution substation belongs to Hydro-Québec, even when it sits on your land; only the civil works do not belong to it.
  • Hydro-Québec remains the owner of what is upstream of the connection point, even if you pay part of the work.
  • The customer remains the owner of the civil works built on the customer’s property (Green Book, 5th edition, 2009).
  • The installation downstream of the connection point is yours: bringing it up to standard, maintaining, adding to and replacing it are your responsibility.

Hydro-Québec must be able to install its equipment on the property free of charge, in places that are easy to reach, safe and agreed with you.

The customer keeps priority on the substation’s full capacity, but Hydro-Québec can supply other customers from that substation.

If it plans to supply neighbours, the additional civil works are at its expense and belong to it (Green Book, 5th edition, 2009).

Who pays what

The owner builds, at the owner’s expense and to Hydro-Québec’s requirements, the civil works located on the property. For a pad-mounted substation supplied underground, these are the pads, splice vaults, vaults for switching and protection devices, and duct banks (Green Book, 5th edition, 2009).

Their maintenance and replacement also remain the owner’s responsibility.

Any landscaping that blends the substation into its surroundings is at the customer’s expense, and must meet Hydro-Québec’s requirements (Green Book, 5th edition, 2009).

The customer also pays for work beyond the basic service. For an extension or modification of an underground line, Hydro-Québec adds up the cost of the cable, transformers and switching equipment, then deducts the value of the basic service.

Hydro-Québec publishes in its Electricity Conditions of Service the price grid for its pad-mounted transformers, per unit, that it uses in this calculation.

A supply method other than the basic service, agreed with Hydro-Québec, is entirely at your expense for the difference.

The master electrician or engineer must warn you that connection or line charges may apply (Green Book, 5th edition, 2009).

The pad and its surroundings

Requirements of Hydro-Québec’s Green Book (5th edition, 2009) for what the customer builds around a pad-mounted substation:

ItemWhat the standard requires
LocationAgreed with Hydro-Québec, for the transformers as for the protection and switching devices
In front of the doorsAt least 4 m of clearance, with no overhanging structure above the pad
Sides1.5 m recommended to walls or obstacles; otherwise at least 1 m (three-phase) or 0.6 m (single-phase) from the building
GroundSlope of at most 5% outward, never toward the equipment; water must not collect around the pad
PadPrecast, from an accredited manufacturer, approved by Hydro-Québec, installed to its standard drawings
CablesSupplied by the customer from the service box to the transformer, with at least 2 m above the pad; at 347/600 V, no more than 15 m to the duct outlet
GroundingBuilt by the customer: four or six 3 m copper-clad steel rods, and a ring buried about 1 m from the pad
TrafficCollision protection if the pad is exposed to cars or less than 1.5 m from a roadway
AccessEntirely outdoor access road, reachable at all times by flatbed truck

The customer’s low-voltage service is underground, and the substation is connected to the line by a duct bank of two or four ducts (Green Book, 5th edition, 2009).

A fence, shed or other uninsulated metal structure located 1 to 3 m from the pad is bonded to the grounding ring (Green Book, 5th edition, 2009).

The pad’s location must also comply with the Québec Construction Code.

The steps

The supply request is made by the owner of the installation or a person the owner mandates. For the subscription request, the Green Book (5th edition, 2009) names the master electrician or the consulting engineer as representative.

Under the same standard, the request includes, among other things, the potential location of the distribution substation.

Before the connection work, still under the Green Book, the customer undertakes in writing to sign an agreement that sets the technical requirements and the financial terms.

Hydro-Québec is notified at least 48 hours, or two business days, before the start of the work to be inspected (Green Book, 5th edition, 2009). One of its representatives must check and accept the civil works before the electrical equipment is installed.

The customer’s protection curves, overlaid on Hydro-Québec’s, must reach it before energization (Green Book, 5th edition, 2009).

According to the Green Book (5th edition, 2009), lead times vary by project and can reach nine months after the required information is received; three months can pass between the acceptance of the civil works and the connection. The customer must check with Hydro-Québec for the lead times of the project.

In Montréal, on the territory of the Commission des services électriques de Montréal (CSEM), its own terms apply to the civil works (Green Book, 5th edition, 2009).

Who does what

Under the Green Book (5th edition, 2009), Hydro-Québec does the electrical work from the line to the connection point, and only Hydro-Québec connects the customer’s installation to the line.

The master electrician is not allowed to connect a new service to Hydro-Québec’s service or to the line.

For the same standard’s capacity I, II, III and VI substations, the connection point is at the transformer’s low-voltage terminals.

The Green Book also provides that Hydro-Québec supplies and installs the connectors for 350, 500, 750 or 1000 kcmil cables; for any other size, the customer supplies and installs the lugs. The customer also marks each cable by phase.

Opening the doors of a pad-mounted transformer without Hydro-Québec’s authorization is prohibited (Green Book, 5th edition, 2009).

Landscaping work that would hinder its access to the substation first requires its authorization.

The dry-type transformer in the building

When a 120/208 V installation is re-supplied at 347/600 V, the equipment downstream of the connection point, step-down transformers included, is at the customer’s expense.

This transformer belongs to the owner. The Régie du bâtiment’s guide (2018 edition of the Code) sets out its basic rules:

  • a disconnecting means on the primary of each transformer;
  • overcurrent protection for each dry-type transformer of 750 V or less;
  • conductors with sufficient ampacity;
  • for a naturally cooled dry-type transformer, at least 150 mm of air between the enclosure and nearby surfaces (floor excepted), and 300 mm from a combustible surface.

The secondary neutral is grounded directly on the transformer’s neutral terminal.

Our role

We install and replace transformers inside buildings, and do our share of the work on a pad-mounted transformer with Hydro-Québec.

For a commercial project, the quote is written and free; it usually arrives within 7 days.

The rest of the work on a commercial building is described on our commercial and industrial electrician page.

Frequently asked questions

Who owns the pad-mounted transformer in front of my building?

Hydro-Québec, even if it is on your land. The pad, duct banks and other civil works you built remain yours (Green Book, 5th edition, 2009).

At what service size is a distribution substation needed?

Under the 2026 Electricity Conditions of Service: when the service boxes total 600 A or more and the maximum current demand exceeds 500 A (600 A for dual energy in winter).

Who pays for the pad?

The owner. Under the Green Book (5th edition, 2009), the owner builds, at the owner’s expense, the pads, vaults and duct banks of a pad-mounted substation supplied underground.

Can the transformer be opened to work on it?

No. Under the Green Book (5th edition, 2009), opening the doors of a pad-mounted transformer requires Hydro-Québec’s authorization, and only Hydro-Québec connects the installation to its line.

How long should we plan for?

According to the Green Book (5th edition, 2009), up to nine months after the required information is received, and sometimes three months between the acceptance of the civil works and the connection. Hydro-Québec gives the lead times for each project.

Can we choose a pole-mounted substation instead of a pad?

Under the Green Book (5th edition, 2009), only if the line is overhead, and not if your enrolment in an undergrounding program is confirmed. The type of substation is chosen with Hydro-Québec.

A project that needs a pad-mounted transformer?

We do our share of the work with Hydro-Québec; the quote for a commercial project usually arrives within 7 days.